Global pharmaceutical company, Connecticut campus
A global pharmaceutical company's facilities team had already run an engineer-led procurement process for an 8 MW onsite solar project. Station A joined as a second-opinion layer — and used marketplace benchmarking to cut project cost by 26% and nine months from the timeline.

26% cost reduction
9 months saved
The facilities team is sophisticated. When they evaluated a large onsite solar project for their Connecticut campus — an 8 MW BTM installation with a $28M+ total project cost — they didn't go in blind. They engaged three engineering firms to develop internal bids and had a credible process in place.
The problem wasn't competence. It was reference data. Without visibility into what comparable projects were actually clearing at in a competitive market, there was no reliable way to know whether the bids they received were sharp or padded. Internal engineer estimates, however rigorous, reflect a desktop view of the market. They don't reflect what a developer will actually accept when competing against peers for a named site.
Station A was brought in to run a parallel competitive process alongside the company's existing internal bids — applying the marketplace to benchmark what the three engineer-led proposals were actually worth relative to a live field of developers competing for the same work.
The result was a clearer picture of market pricing than any desktop study could provide, a third-party ownership structure built to comply with Connecticut's regulatory requirements, and a provider selected on the basis of competitive performance rather than internal preference. Station A also contributed directly to contract negotiations, reducing the back-and-forth that typically extends solar project timelines from award to signed agreement.
Project cost came in 26% below the company's internal cost benchmark. Nine months were cut from the execution timeline versus what the original process would have required. The ownership structure delivered full compliance with local regulatory requirements — something the internal bids had not fully resolved.
It's a clean example of what happens when a sophisticated buyer adds a competitive layer to a process it already runs well. The facilities team didn't need Station A to manage the project from scratch. It needed a market signal. That signal changed the outcome by more than either side had expected at the outset.
Start with a free portfolio screen. No commitment.